WIP Accrued Costs Account
"WIP Accrued Costs Account."
Here's an explanation with an example:
In Microsoft Dynamics 365 Business Central, the WIP (Work In Progress) Accrued Costs Account is used within the Jobs module. It's a balance sheet account where you accumulate the costs of a job that have been recognized but not yet invoiced to the customer.
The recognition of costs depends on the WIP method selected. If you're using the Cost Value or Cost of Sales method, this account comes into play when the recognized costs exceed the costs that have been posted to the job ledger entries as current usage.
Example:
Let's say you have a job for building a custom piece of furniture, and you've chosen to use the Cost of Sales WIP method. Over time, you accumulate various costs such as materials, labor, and overheads, which you post against the job. At the end of the month, you want to recognize revenue based on the percentage of completion.
- If the total costs posted are $10,000 but you recognize, based on completion, that the cost should be $15,000, there is a $5,000 difference.
- This $5,000 is posted to the WIP Accrued Costs Account to show that it's an accrued expense not yet invoiced or matched with revenue. It’s essentially recognizing that you have incurred more costs than you have billed for.
When you invoice the client for this additional cost or when the job is complete and all revenue is recognized, you would then clear out this WIP Accrued Costs Account, moving the balance to the cost of goods sold or another relevant account. This helps maintain accurate financial reporting by matching revenue with the expenses incurred to earn that revenue.